Skip Maine state header navigation
MAINE
SUPREME JUDICIAL COURT
Reporter of Decisions
Decision: 2003 ME 135
Docket: Kno-03-242
Argued: September
29, 2003
Decided: November
26, 2003
Panel: SAUFLEY,
C.J., and RUDMAN, DANA, ALEXANDER, CALKINS, and LEVY, JJ.
ROYCE CARROLL et al.
v.
TOWN OF ROCKPORT et al.
ALEXANDER, J.
[¶1] Royce Carroll and Cindy Salo (Carroll)
appeal from a judgment of the Superior Court (Knox County, Atwood, J.) affirming a vote of
the Town of Rockport Board of Appeals to approve a revised plan for the Mount
Pleasant Subdivision. Carroll
contends that the Superior Court erred when it determined that (1) Carroll's
appeal was filed too late to preserve a challenge to a Board vote approving a
waiver of a 1000-foot dead-end road length limitation; (2) the Board properly
approved revised plans with changed road lengths after initially rejecting a
plan with longer road lengths; and (3) the Board's approach to decision-making
had not improperly shifted the burden of proof to the opponents of the
subdivision. Because the Board
failed to make the findings of fact required by the Town of Rockport Ordinances
and state law, we vacate and remand for further proceedings.
I. CASE HISTORY
[¶2] Lance and Holly Limoges own a 46-acre
parcel of land in the Town of Rockport.
On this land they constructed a home and a private road approximately
1600 feet in length. Royce Carroll
owns land abutting the Limogeses' land.
Cindy Salo is the personal representative of an estate which owns land
within the immediate vicinity of the Limogeses' land.
[¶3] In December 1999, the Limogeses submitted
an application for approval of a thirteen-lot subdivision to the Rockport
Planning Board. Carroll,
Salo, and others objected to the subdivision plans and participated in
the administrative proceedings before the Planning Board and subsequent
proceedings before the Board of Appeals.
Many issues were raised and addressed in the course of consideration
of the subdivision by the Planning Board and the Board of Appeals. However, for purposes of this appeal,
we address in detail only two aspects of the broader subdivision plan—the length and grade of
the road.
[¶4] The Limogeses' initial subdivision plan
included a proposal for a dead-end road, 3477 feet in length, to provide access
to the thirteen lots in the subdivision.
Section VI(A)(3)(c) of the Rockport Subdivision Ordinance states,
"Dead-end streets shall not exceed 1000 feet in length, from centerline of the
feeder street to center of turnaround, and shall be provided with a turnaround
having a minimum outside radius of 65 feet."
[¶5] The proposed subdivision is located on
the side of a hill, and the original plan contemplated a road with an
approximate twelve percent grade.
The Rockport Subdivision Ordinance provides that grades of roadways
serving three or more homes may not exceed eight percent except, with approval
of the Planning Board, a paved section of a private way may have a maximum
grade of ten percent. Rockport
Subdivision Ordinance § VI(A)(3)(a)(*).
The Rockport Land Use Ordinance incorporates by reference the street
design and construction standards of the Subdivision Ordinance. Rockport Land Use Ordinance § 803.1.6.
[¶6] Section IX(A) of the Subdivision
Ordinance grants the Planning Board discretion to waive requirements of the
Subdivision Ordinance when it "finds that extraordinary and unnecessary
hardships may result from strict compliance with these standards or where there are special
circumstances of a particular plan . . . ." (Emphasis added.)
[¶7] The Limogeses requested a waiver from
the Planning Board of the road length and grade requirements of the Rockport
ordinances. Initially, the
Planning Board denied the request for a waiver. The Limogeses then requested findings of fact and, at the
same time, presented a revised plan to the Planning Board. With the revised plan, the Limogeses
presented a new waiver request, addressing only road length. They asserted that the grade issues
were resolved by the plan revisions.
In their road length waiver request, the Limogeses asserted that other
subdivisions had steeper grades and longer dead-end roads than their proposed
subdivision. After reviewing the
revised plan, the Planning Board waived the 1000-foot dead-end street
limitation. However, after several
subsequent meetings, the Planning Board denied the Limogeses' request for
subdivision approval. The
Limogeses requested reconsideration, asserting that one of the planning board
members had a conflict of interest.
The Planning Board denied the motion for reconsideration.
[¶8] On August 10, 2000, the Limogeses
appealed the Planning Board's denial of their subdivision application to the
Board of Appeals. In their appeal
document, the Limogeses requested that the Board of Appeals:
[R]eview and reverse the
planning board's decision of July 12, 2000 and August 9, 2000, concerning the
conflict of interest of one of the members, that member's request to withdraw
his vote, and the vote of the two members who voted against the final
subdivision approval for the reasons that were irrelevant for final approval
and that had been approved on May 16, 2000.
[¶9] As it was authorized to do,[1]
the Board of Appeals reviewed de novo the Planning Board's denial of the
Limogeses' subdivision application.
The Board of Appeals conducted many meetings and hearings addressing the
subdivision. Most of the
deliberations focused on the question of whether the proposed subdivision
should receive a waiver from the 1000-foot dead-end road length limit. More general concerns were raised
regarding public safety and the impact that subdivision approval would have on
abutting, active blueberry fields.
On July 11, 2001, the Board of Appeals voted to deny the Limogeses'
request for a waiver of the dead-end road length limit. The Board issued no findings regarding
the denial of the waiver request and did not issue any written decision other
than what appears in the minutes of the Board meeting.
[¶10] Following the Board of Appeals action
on the waiver, the Limogeses indicated that they would file a new subdivision
plan for review by the Board of Appeals.
Carroll objected, arguing that any new plan would be a new subdivision
application that should be referred to the Planning Board for review. The Limogeses then submitted, and the
Board of Appeals proceeded to consider, two new plans. Each was essentially the same as the
prior subdivision plan except that the subdivision was reduced to eleven lots. In one alternative plan, road length
was reduced to 3038 feet and in the other alternative road length was reduced
to 2959 feet.
[¶11] On October 3 and November 7, 2001, the
Board voted to waive the 1000-foot dead-end road limit and approve the private
way option with the 2959-foot road length. In other meetings, the Board addressed other criteria stated
in the Subdivision Ordinance and in 30-A M.R.S.A. § 4404 (1996 & Supp.
2002). During the course of this
consideration, the Limogeses submitted further modifications to their plan on
or about December 4, 2001. At its
meeting on December 19, 2001, the Board of Appeals approved the modified
subdivision plan. At that same
meeting, the Board signed the private way plan.
[¶12] The Board of Appeals issued a document
entitled "Mount Pleasant Findings of Fact" on December 26, 2001. The portion of the document entitled
"Findings and Criteria" is not a written decision or findings of fact. Instead, it appears to be the compiled
minutes of Board meetings. In the
document, various motions made at the Board meetings are stated. After the motion is stated, the votes
of the individual Board members are indicated along with paraphrasing, by the
Board secretary, of some Board members' statements of the reasons for their
vote on the particular motion.
[¶13] For example, a portion of the December
26, 2001 document addressing the road length waiver reads as follows:
This Board considered the
following State Criterion No. 9 at the June 20, 2001, June 26, 2001
and July 11, 2001 meetings: "Conformity
with Local Ordinances and Plans — The proposed
subdivision conforms with a duly adopted Subdivision regulation or ordinance,
comprehensive plan, development plan or land use plan, if any."
The controversy
presented by this motion is the issue of the road length waiver. After hours of discussion and debate
Geoffrey Parker made the following motion which was seconded by Donald
Isikoff: "To find the project
on plan prepared by Coffin Engineering is in conformity with all ordinances
except for the length of the road, and to grant the applicant a waiver to allow
the full length of the road applied for with the additional condition that the
road is a private road and will be maintained by the developer". This motion was defeated by vote of
3-2, as follows:
Donald Isikoff -
No: Recognizing that the Board
will be addressing the rest of the issues and open to the possibility of
revisiting the question of road length in the course of that review.
Alan Kumble — No.
R.J. Masiello — Yes.
Geoffrey Parker — No.
Victor Steinglass —
Yes: Per page 22 of the Subdivision
Ordinance, in his opinion it is appropriate to this private way to have this
waiver.
The Chairman advised
that Board will continue to review:
Pollution, Erosion, Ground water and Stormwater.
At the October 3, 2001
meeting this Board again considered the issue of the road length waiver when
the applicant presented a new road design called Option 2 (see Subdivision
Ordinance Section VI(3)(f)).
Donald Isikoff made the following motion which was seconded by Geoffrey
Parker: "To accept road design Option
2 at 2,959 feet in length for the Limoges Subdivision," and this motion
was amended to include the condition that the subdivision road shall always
remain private. The amended motion to allow the waiver
of the road length was passed by a 3-2 vote, as follows:
Donald Isikoff —
No: Based on his statements in the
record.
Alan Kumble — Yes.
Geoffrey Parker — No.
R. J. Masiello — Yes.
Victor Steinglass —
Yes: Objective testimony has been
received that does not provide any reason to question whether the road length
is inappropriate and that has indicated that the road is safe.
At the same October 3,
2001 meeting Geoffrey Parker made the following motion which was seconded by
R.J. Masiello: "To find the
proposed Limoges subdivision, with Option 2 revision, in conformity with all
ordinances and plans as described in No. 9 of the review criteria, with the
previously passed road waiver."
This motion passed by a 3-2 vote, as follows:
Geoffrey Parker — No:
Having taken this issue very seriously and agonized over the decision, he has
ultimately had a difficult time coming to the conclusion of finding the project
conforms with local ordinances and Comprehensive Plan.
Donald Isikoff —
No: This project still conflicts
with the Purpose section of the Comprehensive Plan.
R.J. Masiello — Yes:
Based upon information available:
Alan Kumble — Yes: Board members have read similar things
and come to different conclusions.
An important point of Section 908-1-Purpose is balancing other issues against
unlimited development. He would
rather this project did not happen, but equity must play a role and he cannot
see any legal reason not to approve it.
Victor Steinglass —
Yes: He agreed that the limited
development is a moving target, but feels the project meets the essence and
intent of limited development and does comply with Comprehensive Plan, Land Use
Ordinance and Subdivision Ordinance.
The total "Findings and
Criteria" covers nine pages.
[¶14] Carroll's appeal to Superior Court,
pursuant to M.R. Civ. P. 80B, was filed on January 14, 2002. The Superior Court, after a hearing,
dismissed, as untimely, the portion of Carroll's appeal relating to approval of
the private way permit. The
Superior Court reasoned that Carroll's appeal was untimely, as the private way
permit had been approved by the oral vote of November 7, 2001. In all other respects, the Superior
Court affirmed the Board of Appeals approval of the subdivision. Carroll then brought this appeal.
[¶15] Carroll contends that the July 11, 2001,
vote of the Board of Appeals, denying the waiver of the road length
requirement, was a final decision on that issue and, consequently, on the
application for approval of the subdivision. From that point, Carroll argues, any revised subdivision
plan should have first been presented to the Planning Board, as the agency of
original jurisdiction. The
Limogeses assert that the November 7, 2001, vote approving the waiver of the
1000-foot limitation for their revised plan is a final decision of the Board of
Appeals which Carroll was required to appeal within forty-five days pursuant to
30-A M.R.S.A. § 2691(3)(a) (1996).[2] The Limogeses also contend that the
December 26, 2001 "Findings of Fact" is a sufficient recordation of the
December 19, 2001, actions of the Board of Appeals to constitute a final
written decision, including the fact-findings required by both the Rockport
Land Use Ordinance and state law.
II. LEGAL ANALYSIS
A. Finality of Board
Actions
[¶16] Absent special and narrow exceptions,
appeals may only be considered from final judgments, or final rulings of
administrative agencies. See
Rockland Plaza Realty Corp. v. City of Rockland, 2001 ME 81, ¶ 6, 772
A.2d 256, 258; Lakes Environtmental Ass'n v. Town of Naples, 486 A.2d 91, 95-96
(Me. 1984). A final judgment or
final administrative action is a decision that fully decides and disposes of
the entire matter pending before the court or administrative agency, leaving no
questions for the future consideration and judgment of the court or
administrative agency. See In
Re Adoption of Matthew R., 2000 ME 86, ¶ 5, 750 A.2d 1262, 1264; Mechanic Falls
Water Co. v. Public Utilities Comm'n, 381 A.2d 1081, 1087 (Me. 1977); Hazzard v.
WestView Golf Club, Inc., 217 A.2d 217, 222 (Me. 1966); accord Musson v. Godley, 1999 ME 193, ¶ 5, 742
A.2d 479, 481.
[¶17] Findings of fact and conclusions of law
reached by an administrative agency in the course of its deliberations, but
prior to issuance of a final decision, are not final administrative actions. Although the administrative
decision-making may have indicated what action the administrative agency might
take with respect to a particular issue, such decisions are not sufficient to
transform the fact-findings or legal conclusions into a final order or
judgment. Mechanic Falls Water
Co.,
381 A.2d at 1087.
[¶18]
As this case demonstrates, with
several preliminary administrative decisions approving and disapproving the
waiver of the 1000-foot limit, no local decision-making process can be
considered over until it is over.
Boards of Appeals, like other decision-making bodies, are subject to
change of mind and change of membership which can sometimes lead to change of
result between preliminary and final decision-making. See Sawyer Environmental Recovery Facilities, Inc. v.
Town of Hamden,
2000 ME 179, ¶¶ 8-11, 760 A.2d 257, 259-60 (noting the Town's change of
position during consideration of a land use application).
[¶19] Votes or decisions addressing
individual issues during the course of consideration of an application that
requires rulings or fact-findings on several points are not final
decisions. A person is not
required to file an appeal to protect a challenge to each particular decision,
prior to issuance of a final decision on the overall application.
[¶20] Neither the July 11, 2001, vote against
waiving the 1000-foot limit nor the October 3, 2001, or November 7, 2001, votes
for waiving the 1000-foot limit were final decisions. There is no rule of law that requires that a first, or
third, or fifth decision on a particular issue be the final decision where, as
here, an agency has authority to consider an application de novo and to allow
amendments of an application during the course of its consideration. At some point, excessively long,
repeated, and inconsistent consideration of an issue, without a final result,
may become a due process concern, but no such issue is presented here.
[¶21]
After the Board of Appeals' July 11, 2001, vote rejecting the waiver,
the Limogeses were not required to cease participation before the Board of
Appeals and file any amended plans as new proceedings before the Planning
Board.[3] Likewise, after the November 7, 2001,
vote approving the waiver, Carroll was not required to file an appeal within
thirty or forty-five days or waive the right to challenge approval of the
waiver. The vote of November 7 was
not confirmed until the final approval of the subdivision on December 19 and
adoption of the purported findings of fact on December 26, 2001.
[¶22] The Limogeses assert that our decision
in Vachon v. Town of Kennebunk, 499 A.2d 140 (Me. 1985), and the statutes
governing appeals from the Board of Appeals specify that the time for appeal
began to run from the vote on November 7 and not from issuance of the
decision. The Limogeses' argument
is unclear as to why the time for appeal should begin to run from the November
7 vote instead of the July 11 vote, the October 3 vote, or any of the other
preliminary votes that were taken in the course of consideration of their
subdivision application. Focusing
on November 7, 2001, they point to the language of Vachon which states that the
appeal period "should start to run immediately when the Board took its final
public action, both because that time is easily determined and precisely fixed
and because all parties to the public proceeding will ordinarily know of the
Board's public vote at the time it is taken." Id. at 142. In Vachon, our reference to the
"final public action" addressed the final approval or disapproval of an
application when a board casts its public vote. Id. Here, that
final approval or disapproval occurred with the December 19 vote, confirmed by
the December 26 issuance of the purported findings of fact.
[¶23] State law governing appeals from boards
of appeals, 30-A M.R.S.A § 2691(3)(G) (1996), is consistent with this
interpretation. Subparagraph 3(G)
states: "Any party may take an appeal, within 45 days of the date of the vote
on the original decision, to Superior Court from any order, relief or denial in
accordance with the Maine Rules of Civil Procedure, Rule 80B." We will not infer that the Legislature
intended an illogical or absurd result in a statute it enacted. Brent Leasing Co. v. State Tax
Assessor,
2001 ME 90, ¶ 6, 773 A.2d 457, 459.
The "date of the vote on the original decision" necessarily means the
vote finally approving or disapproving an appeal or an application, not any of
the many preliminary votes that may be taken in the course of consideration of
an appeal or an application.
[¶24] Because Carroll's appeal was filed
within forty-five days of the date of the final vote on the administrative
appeal, the Superior Court erred in dismissing Carroll's appeal of the Board of
Appeals approval of the waiver of the 1000-foot limit.
B. Sufficiency of
the Board of Appeals Decision
[¶25] The Rockport Land Use Ordinance
authorizes the Board of Appeals to consider requests to waive specific
requirements of land use laws or ordinances in proceedings to approve a special
exception (Rockport Land Use Ordinance § 703.3) or a variance (Rockport
Land Use Ordinance § 703.4). The
Rockport Subdivision Ordinance authorizes the Planning Board to waive specific
requirements of that ordinance after making certain findings. Rockport Subdivision Ordinance §
IX. It is unclear from the record
which of these provisions the Board of Appeals applied in its consideration of
the Limogeses' request to waive the road length limitation. The special exception, variance, and
waiver provisions each require an applicant to meet certain listed criteria to
qualify for a special exception, a variance, or a waiver. The burden is on the applicant to
establish that the criteria for a special exception, variance, or waiver are
met. Rockport Subdivision
Ordinance § V, Rockport Land Use Ordinance §§ 703.3, 703.4. See also Lewis v. Town of
Rockport,
1998 ME 144, ¶ 15, 712 A.2d 1047, 1050 (burden of proving compliance with an ordinance
is on the applicant).
[¶26] In decisions resulting from any of
these proceedings, specific findings are required. Thus, 30‑A M.R.S.A. § 2691(3)(E) (1996) specifies that
decisions by local boards of appeal "must include a statement of findings and
conclusions, as well as the reasons or basis for the findings and conclusions,
upon all the material issues of fact, law or discretion presented . . . ." Separately, Maine's Freedom of Access
law specifies that, when any local agency conditionally approves or denies any
permit, the agency shall make a written record of the decision and "shall set
forth in the record the reason or reasons for its decision and make finding of
the fact [sic],
in writing, sufficient to apprise the applicant and any interested member of
the public of the basis for the decision." 1 M.R.S.A. § 407(1) (1989). Because the Limogeses' application was
approved with conditions, specific findings were required by both statutes.
[¶27] When administrative agencies are
required to make findings of fact to support a decision, the findings must be
adequate to indicate the basis for the decision and to allow meaningful
judicial review. In Chapel Road
Associates v. Town of Wells, 2001 ME 178, ¶ 10, 787 A.2d 137, 140, we observed:
Meaningful judicial
review of an agency decision is not possible without findings of fact
sufficient to apprise the court of the decision's basis. Christian Fellowship & Renewal
Ctr. v. Town of Limington, 2001 ME 16, ¶¶ 10-15, 769 A.2d 834, 837-39. In the absence of such findings, a
reviewing court cannot effectively determine if an agency's decision is
supported by the evidence, and there is a danger of "judicial usurpation of
administrative functions." Id. ¶ 15, 769 A.2d at 839
(quoting Gashgai v. Bd. of Registration in Med., 390 A.2d 1080, 1085
(Me. 1978)). Adequate findings
also "assure more careful administrative considerations, help parties plan
cases for rehearing or judicial review and . . . keep agencies within their
jurisdiction." Id. (quoting Maine
AFL-CIO v. Superintendent of Ins., 595 A.2d 424, 428 (Me. 1991)); see also
Harrington v. Inhabitants of Town of Kennebunk, 459 A.2d 557, 561-62
(Me. 1983) (remanding matter to agency in zoning context where findings were
insufficient to allow judicial review).
[¶28] The requisite findings of fact may be
stated in a written order or stated orally and then transcribed in a written
order. However, an oral statement
purporting to be findings of fact to support a decision must be sufficiently
clear to be reviewable. Further,
the findings, whether in writing or stated orally, must be a statement of the
decision-maker's findings, not the views of individual members of the
decision-making agency.
[¶29] In Widewaters Stillwater Co. v.
Bangor Area Citizens Organized for Responsible Development, 2002 ME 27, ¶¶ 9-12,
790 A.2d 597, 600-01, we reviewed rejection of an application for development
of a shopping center. The
available written record included no specific written findings, only statements
in the record by individual board members reflecting their individual opinions
as to why they were voting as they did on the particular question or questions
presented. The individual
statements did not represent any collective judgment of the fact-finding agency
regarding the application.
Accordingly, we vacated and remanded the agency decision for development
of proper fact-findings upon which review could be based. Id.
[¶30] As we stated in Christian Fellowship
and Renewal Center v. Town of Limington, 2001 ME 16, ¶¶ 14-18, 769 A.2d 834, 838-40,
and as we repeated in Widewaters, 2002 ME 27, ¶ 12, 790 A.2d at 601, when an
administrative board or agency fails to make sufficient and clear findings of
fact and such findings are necessary for judicial review, we will remand the
matter to the agency or board to make the findings.
[¶31] The Board of Appeals secretary's
paraphrasing of the reasons given by some, but not all, of the Board members
for their votes on various issues, including those relating to waiver of the
1000-foot dead-end road limitation, are not findings. These individual comments
do not inform us of the findings which the Board of Appeals was required to make
as part of its decision, nor do they inform us as to whether the review of the
waiver of the 1000-foot limit was conducted according to standards of review
for a special exception, for a variance, or for a waiver. Further, the document purporting to be
findings does not appear to address the issue of compliance with the maximum
grade requirements specified in the Land Use Ordinance and the Subdivision
Ordinance. Accordingly, we vacate
the decision of the Superior Court and remand for determination of whether the
application is being considered as a special exception, a variance, or a
waiver. Once the status of that
review is determined, the Board of Appeals should proceed to make findings that
represent its collective judgment, addressing each factor that must be
considered under the law that the Board is applying in reviewing the
application.[4]
The
entry is:
Judgment vacated. Remanded to the Superior Court for
remand to the Board of Appeals of the Town of Rockport for further
consideration in accordance with this opinion.
______________________
Attorney for plaintiffs:
David J. Perkins, Esq. (orally)
Perkins Olson, P.A.
P O Box 449
Portland, ME 04112-0449
Attorneys for defendants:
Amy K. Tchao, Esq.
William L. Plouffe, Esq.
Drummond Woodsom & MacMahon
P O Box 9781
Portland, ME 04104-5081
(for Town of Rockport)
Clifford H. Goodall, Esq. (orally)
Thomas B. Federle, Esq.
Mary A. Dennison, Esq.
Dyer Goodall and Federle, LLC
61 Winthrop Street
Augusta, ME 04330
(for Land & Holly Limoges)
[1] See Rockport Land Use Ordinance §§ 703 and 706.
[2] As a time limit "specified by statute" the forty-five-day time limit for bringing M.R. Civ. P. 80B appeals from decisions of local boards of appeal is an exception to the usual thirty-day limit for filing appeals specified in M.R. Civ. P. 80B(b). Notably, the Rockport Land Use Ordinance specifies two time limits for bringing appeals from Board of Appeals decisions. Section 702.7 sets a forty-five-day from "date of the vote" limit as specified in 30-A M.R.S.A. § 2691(3)(G). Section 705.4 specifies a "30 days after the decision" limit, citing 30 M.R.S.A. § 2411 which was repealed by P.L. 1987, ch. 737, § A, 1 (effective February 28, 1989).
[3] When an applicant presents an entirely new plan, rather than adjusting a pending proposal to address Board of Appeals' concerns, the new plan should be presented to the Planning Board.
[4] When a board vote is divided, only findings which reflect the majority vote need be stated as findings. See Widewaters, 2002 ME 27, ¶ 11, 790 A.2d at 601.