Skip Maine state header navigation
MAINE SUPREME JUDICIAL COURT
Reporter of Decisions
Decision: 2005 ME 88
Docket: Han-04-178
Argued: October 20, 2004
Decided: July 7,
2005
Panel: SAUFLEY,
C.J., and CLIFFORD, DANA, ALEXANDER, CALKINS, and LEVY, JJ.
ANTHONY
ULIANO et al.
v.
BOARD
OF ENVIRONMENTAL PROTECTION et al.
LEVY, J.
[¶1] Anthony and Erin Uliano appeal from a
judgment of the Superior Court (Hancock County, Mead, J.) affirming the Board of Environmental Protection's
order denying their application for a permit to build a pier pursuant to the
Natural Resources Protection Act (NRPA, the Act), 38 M.R.S.A. §§ 480-A to
480-AA (2001 & Supp. 2004).
The Ulianos raise several challenges to the Board's findings and conclusions. We conclude that the Board misapplied
its Wetland Protection Rules and failed to issue findings that permit effective
appellate review. Accordingly, we
vacate the judgment and remand this matter for additional proceedings by the
Board.
I. BACKGROUND
[¶2] The
Ulianos own waterfront property in Salsbury Cove on Eastern Bay in Bar
Harbor. Their NRPA permit
application seeks approval to construct a 95' x 6' private,
recreational pier, with an attached 50' seasonal aluminum ramp and a 16' x 20'
seasonal wooden float. The Ulianos
need a permit because building the pier will constitute construction of a
permanent structure in, on, or over coastal wetlands, which are a protected
natural resource. 38 M.R.S.A.
§§ 480‑B(2), (8), 480-C (2001 & Supp. 2004).
[¶3] The
Department of Environmental Protection received numerous letters in opposition
to the Ulianos' permit application, many of which requested a public hearing
before the full Board.[1] The letters expressed concern that the
pier will threaten scenic and recreational uses of Salsbury Cove, and harm marine
and wildlife habitats. The Board
declined to assume jurisdiction over the application, and the Department held a
public meeting to receive comment on the proposed pier. The Department ultimately approved the
Ulianos' permit application.
[¶4] Abutters
to the Ulianos' property appealed the Department's decision to the Board
pursuant to 38 M.R.S.A. § 341-D(4) (2001). The Board reversed the Department's decision and denied the
permit application, based on its conclusions that (1) the use of a dinghy in conjunction
with a mooring is a practicable alternative to the pier, 2 C.M.R. 06 096 310-4,
310-7 §§ 5(A), 9(A) (2002); (2) the cumulative impact of the pier,
together with the potential that other piers could follow, poses a substantial
threat to the scenic and aesthetic values of Eastern Bay and Salsbury Cove,
2 C.M.R. 06 096 310-5 § 5(D)(1)(d) (2002); and (3) the pier will
unreasonably interfere with existing scenic and aesthetic uses in a manner
inconsistent with existing structures and development, 38 M.R.S.A.
§ 480‑D(1) (2001).
[¶5] The Ulianos appealed the Board's
decision to the Superior Court pursuant to M.R. Civ. P. 80C, and the Superior
Court affirmed the Board's order.
This appeal followed.
II. DISCUSSION
[¶6] "When the Superior Court acts as an
intermediate appellate court, reviewing a decision of a state or local
administrative agency, we review directly the decision of the administrative
agency." Hannum v. Bd. of
Envtl. Prot., 2003 ME 123, ¶ 11, 832
A.2d 765, 768. Accordingly, we
review the Board's decision for errors of law, unsustainable exercises of
discretion, or findings not supported by substantial evidence in the
record. Id. ¶ 11, 832 A.2d at 768-69; see also 5 M.R.S.A. § 11008 (2002).
A. Whether the
Board's Findings Are Contrary to the Evidence and Arbitrary and Capricious
[¶7] Section 480-D of NRPA sets forth nine standards that an
applicant must meet to receive a permit for activities that are regulated by
the Act.[2] 38 M.R.S.A. § 480‑D
(2001 & Supp. 2004). "[T]o
ensure that the standards set forth in [s]ection 480-D . . . are met by
applicants proposing regulated activities in, on, over or adjacent to a wetland
or water body," the Board promulgated the Wetland Protection Rules. 2 C.M.R. 06 096 310‑2 § 1
(2002). The Wetland Protection
Rules set forth a framework of factors, including practicable alternatives and
cumulative impact standards, to be considered by the Board and the Department
when conducting section 480-D analyses.[3] 2 C.M.R. 06 096 310 (2002).
[¶8] The Ulianos challenge the Board's findings and conclusions
pertaining to its (1) practicable alternatives analysis; (2) cumulative
impact analysis; and (3) section 480-D(1) analysis. We consider each in turn.
1. Practicable Alternatives
[¶9] Section 5(A) of the Wetland Protection
Rules states that "[n]o activity shall be permitted if there is a practicable
alternative to the project that would be less damaging to the
environment." 2 C.M.R. 06 096
310-4 § 5(A). "Practicable" is defined as "[a]vailable and feasible considering
cost, existing technology and logistics based on the overall purpose of the
project." 2 C.M.R. 06 096 310-3
§ 3(R) (2002). Section 5(A)
further specifies that each permit application "must provide an analysis of
alternatives [pursuant to section 9(A)] in order to demonstrate that a
practicable alternative does not exist."
2 C.M.R. 06 096 310-4, 310-7 §§ 5(A), 9(A). Determining whether a practicable
alternative exists includes:
(1) Utilizing,
managing or expanding one or more other sites that would avoid the wetland
impact;
(2) Reducing
the size, scope, configuration or density of the project as proposed, thereby
avoiding or reducing the wetland impact;
(3) Developing
alternative project designs, such as cluster development, that avoid or lessen
the wetland impact; and
(4) Demonstrating
the need, whether public or private, for the proposed alteration.
2 C.M.R.
06 096 310-7 § 9(A).
[¶10] The purpose of the Ulianos' proposed
pier, as stated in their permit application, is to provide access to their boat
at all tides. Among other
alternatives, the Ulianos considered, but rejected, using a dinghy and a
mooring in lieu of a pier.[4]
[¶11] The Board found that using a dinghy and
a mooring is a practicable alternative to the proposed pier and, thus, the
Ulianos did not meet their burden of proving that no practicable alternative
exists. The Board did not,
however, relate its finding that a practicable alternative exists to its
overall determination of whether the relevant section 480-D criteria were
satisfied. The Board simply
discussed the evidence in the record regarding practicable alternatives and
concluded that the Ulianos did not meet their burden of proving that no
practicable alternative to their pier exists. For the reasons that follow, we conclude that the Board
erred as a matter of law in undertaking its practicable alternatives analysis
in isolation from the statutory permitting standards set forth in
section 480‑D.
[¶12] The Board promulgated the Wetland
Protection Rules to ensure that the standards contained in section 480-D are
met. 2 C.M.R. 06 096 310-2 §
1. The Board argues that the rules
are a part of its overall analysis, and we are persuaded by its argument that
an applicant's adherence to the rules is one factor the Board must consider to
determine whether the section 480-D criteria are met. This means that section 5(A) of the rules is not an independent
criterion, but is only a factor to be considered by the Board, and an
applicant's failure to comply with one of the rules may support, but does not
compel, a determination that a project's impact on a protected natural resource
would be unreasonable.
[¶13] The specific standard at issue in this
case is described in section 480‑D(1), which provides that to obtain a
permit for a proposed project an applicant must demonstrate that the project
"will not unreasonably interfere with existing scenic, aesthetic, recreational
or navigational uses." 38 M.R.S.A.
§ 480‑D(1). Whether a
proposed project's interference with existing uses is reasonable depends on a
multiplicity of factors, one of which is the existence of a practicable
alternative. A balancing analysis
inheres in any reasonableness inquiry.
See Grant's Farm Assocs., Inc. v. Town of Kittery, 554 A.2d 799, 802 (Me. 1989). Therefore, the Board's consideration of
practicable alternatives to a proposed project is a factor that should be
balanced in its section 480-D(1) analysis.
[¶14] The Board might find, for example, that
the existence of a practicable alternative does not justify the denial of a
proposed project if the degree of interference the project will cause to
existing uses is insubstantial.
Conversely, the Board might find that the existence of a practicable
alternative supports the denial of a project if it finds that the degree of the
project's interference with existing uses will be substantial. In the latter case, the Board may conclude
that, on balance, the resulting interference with existing uses would be
unreasonable because of the existence of a practicable alternative that, if
pursued, would enable the applicant to accomplish the project's objectives
through alternate means.
[¶15] Although we did not expressly adopt such
an interpretation of the practicable alternatives rule in our recent discussion
of the rule in Kroeger v. Department of Environmental Protection, 2005 ME 50, 870 A.2d 566, treating the practicable
alternatives rule as a factor to be balanced in the Board's section 480‑D(1)
analysis is consistent with our application of the rule in that case. In Kroeger, we noted that the Department determined that a
proposed dock's interference with existing scenic and aesthetic uses would be
unreasonable because practicable alternatives to the dock existed. Id. ¶ 17, 870 A.2d at 571. The Department discussed its practicable alternatives
findings in terms of the reasonableness of the proposed dock's interference
with existing scenic and aesthetic uses.
Id. Hence, the existence of a practicable
alternative to a proposed project supported, but did not compel, the
administrative decision to deny the permit pursuant to section 480-D(1). Id. ¶ 20, 870 A.2d at 572.
[¶16] In contrast with the approach taken in Kroeger
and described by the Board in its brief to
us, the Board's order in this case did not treat the practicable alternatives
rule as a factor to be considered in its section 480-D(1) balancing
analysis. Rather, the Board
concluded that the use of a dinghy and a mooring is a practicable alternative
to the proposed pier, and made no effort to factor that finding into its
ultimate determination of whether the Ulianos' proposed pier will "unreasonably
interfere with existing scenic, aesthetic, recreational or navigational
uses." 38 M.R.S.A. § 480‑D(1). The practicable alternatives standard
was not applied as a factor, but rather as an independent, determinative criterion.
[¶17] Accordingly, we conclude that the Board
erred as a matter of law in its application of the practicable alternatives standard. On remand, the Board should reconsider
its practicable alternatives findings and apply those findings as part of its
section 480‑D(1) analysis. [5]
2. Cumulative
Impact
[¶18] Section
5(D)(1) of the Wetland Protection Rules states, "[e]ven if a project has no
practicable alternative and the applicant has minimized the proposed alteration
as much as possible, the application will be denied if the activity will have
an unreasonable impact on [a] wetland."
2 C.M.R. 06 096 310-5 § 5(D)(1) (2002). "'Unreasonable impact' means that one or more of [section
480-D's standards] will not be met."
Id. In determining whether an activity will
have an unreasonable impact, the Department considers, among other things, "[c]umulative effects of frequent minor
alterations on [a] wetland." 2
C.M.R. 06 096 310-5 § 5(D)(1)(d).
[¶19] The
Board found that "the cumulative impact of the [Ulianos'] pier, together with
the potential that other piers could follow, poses a substantial threat to the
scenic and aesthetic values of Eastern Bay and Salsbury Cove." Citing our decision in Hannum, the Ulianos assert that this finding is contrary to
the evidence and arbitrary and capricious because the Board's speculation that
other piers might follow should their pier be approved cannot serve as a basis
for deciding that the cumulative impact standard was not met.[6] See 2003 ME 123, ¶ 15 n.6, 832 A.2d at 770 (holding that
"[f]act-finders must rely on evidence, not speculation, in fact-finding").
[¶20] The Board concedes that its speculation
was improper in light of Hannum, which
was issued after the Board acted on the Ulianos' permit application. Furthermore, as with the practicable
alternatives standard, the Board did not tie its application of its cumulative
impact standard to its section 480-D(1) analysis. Therefore, on remand, the Board must issue additional
findings regarding the cumulative impact of the Ulianos' pier and incorporate those findings into its section 480-D(1)
analysis.
3. Section 480-D(1) Findings
[¶21] As previously noted, section 480-D(1)
provides that in order to obtain a permit to build their pier the Ulianos had
to prove that the pier "will not unreasonably interfere with existing scenic,
aesthetic, recreational or navigational uses." 38 M.R.S.A. § 480‑D(1). Based
upon the evidence in the record and its observations, the Board concluded that
the Ulianos' pier will unreasonably interfere with existing scenic and
aesthetic uses. The Ulianos argue
that this conclusion is contrary to the evidence and arbitrary and capricious.
[¶22] The Ulianos had the burden of proving
that their pier will comply with section 480-D(1). See Hannum, 2003 ME 123, ¶ 12, 823 A.2d at 769. Concomitantly, the Board "had an
affirmative obligation to set out in a decision its reasons for the denial of
the application and to state its reasons with sufficient specificity to permit
understanding and meaningful appellate review." Id. See also 1 M.R.S.A. § 407(1) (1989); 5 M.R.S.A. § 9061 (2002).
[¶23] The Board based its conclusion that the
Ulianos' pier will unreasonably interfere with existing scenic and aesthetic
uses on the following findings:
The record contains
photographs, maps and descriptions of the shoreline in the area of the proposed
project. Members of the Board also
visited the site to assess potential impacts to scenic and aesthetic uses and
therefore finds that additional scenic impact analysis of Eastern Bay is not
warranted. Based on evidence in
the record and observations during its site visit, the Board finds that . . .
the character of the area from Parker Point west to Hadley Point would not be
maintained were the proposed pier constructed and that the project would
unreasonably interfere with existing scenic and aesthetic uses in a manner
inconsistent with existing structures and development.
These findings do not permit meaningful appellate
review because they merely summarize the evidence considered and state the
Board's conclusion. They fail to
identify which scenic and aesthetic uses the Board considered, and they fail to
explain why the Ulianos' pier would unreasonably interfere with those uses.
[¶24] Examples of the types of specific
factual findings that are required are found in Kroeger. In Kroeger, the Department based its decision that the proposed
dock would constitute an unreasonable interference with existing scenic and
aesthetic uses on the following findings: Somes Sound, the location of the
proposed dock, is "'the only natural fjord on the east coast of the United
States'"; "Acadia National Park is located on the opposite side of Somes Sound
from the proposed dock"; "'a light colored, linear structure 17 feet high and
extending out into the sound represents a sharp visual contrast to the natural
horizontal banding of the shoreline, and would degrade the scenic character of
the natural shoreline of the Somes Sound fjord'"; "Somes Sound is used by many
boaters to enjoy the beauty of the area"; and launching small boats from the
shore or utilizing a nearby public marina were practicable alternatives to the
proposed dock. 2005 ME 50,
¶¶ 10, 14, 20, 870 A.2d at 569-72.
These findings permitted appellate review of the Department's denial of
Kroeger's permit because they established the uses the Department considered—the scenic uses of
boaters in the Sound and visitors to nearby Acadia; the significance of the
protected natural resource that would be affected—the only natural fjord
on the east coast of the United States, see 38 M.R.S.A. § 480-A (2001) (explaining that NRPA
protects resources that have "great scenic beauty and unique characteristics,
[and] unsurpassed recreational, cultural, historical and environmental value of
present and future benefit"); and how
construction of the proposed dock would unreasonably interfere with those
uses—detailing how the dock would degrade the Sound's scenic
character. Kroeger, 2005 ME 50, ¶¶ 10, 14, 870 A.2d at 569-70.
[¶25] In contrast with Kroeger, the Board's
findings in the present case provide little insight as to why the Board denied
the Ulianos' permit application.
Without adequate findings, we cannot determine whether the evidence
supports the Board's findings or whether its findings are arbitrary and
capricious. See Christian Fellowship & Renewal Ctr. v. Town of
Limington, 2001 ME 16, ¶ 15, 769 A.2d
834, 839. Moreover, as discussed
above, the Board divorced its practicable alternatives and cumulative impact
findings from its section 480-D(1) analysis. Thus, we conclude that the Board's findings are inadequate
as a matter of law. On remand, the
Board must reconsider the evidence, issue new findings, and undertake a new
section 480-D(1) analysis.
B. The
Ulianos' Remaining Arguments
[¶26] The Ulianos also argue that section
480-D(1)'s scenic and aesthetic uses standard is an unconstitutional delegation
of legislative authority, that the cumulative impact and practicable
alternatives standards in the Wetland Protection Rules are unconstitutionally
vague and exceed the Board's rule-making authority, and that the Board's order
deprived them of their common law right to wharf out. We decline to address
these additional arguments because, depending on the nature of the findings and
conclusions that the Board makes on remand, they may be rendered moot.
The entry
is:
Judgment
vacated and remanded to the Superior Court for an order remanding to the Board of
Environmental Protection for further proceedings consistent with this
opinion.
_____________________
Attorneys for
plaintiffs:
Edmond J. Bearor,
Esq. (orally)
Timothy A. Pease,
Esq.
Rudman &
Winchell
P.O. Box 1401
Bangor, ME 04401
Attorneys for
defendants:
G. Steven Rowe,
Attorney General
Margaret A.
Bensinger, Asst. Atty. Gen. (orally)
6 State House
Station
Augusta, ME
04333-0006
Intervenors:
James & Phoebe
Boyer
P.O. Box 25
Salisbury Cove, ME
04672
David Dunton
Box 1393 State
Highway 3
Bar Harbor, ME
04609
Franklin &
Sherrie Epstein
294 Buckminster
Road
Brookline, MA 02445
Robert & Judith
Grossart
P.O. Box 119
Salisbury Cove, ME
04672
Lois Hager
8 Duncaster Road
Bloomfield, CT
06002
David & Mary
Opdyke
P.O. Box 44
Salisbury Cove, ME
04672
Brad & Lynn
Thompson
42 Lebrun Court
Galveston, TX 77551
[1]
Generally, the Department has jurisdiction
over NRPA permit decisions.
See, e.g., 38 M.R.S.A.
§§ 480-C, 480-D (2001 & Supp. 2004). But, "[a]ny person may request that the Board assume jurisdiction
over an application by submitting the request to the Department in
writing no later than 20 days after the application is accepted as
complete for processing."
2 C.M.R. 06 096 002-8 § 17(A) (2003).
The Board assumes jurisdiction over applications that "(1)
involve[] a policy, rule or law that the Board has not previously
interpreted; (2) involve[] important policy questions that the Board
has not resolved; (3) involve[] important policy questions or interpretations
of a rule or law that require reexamination; or (4) [are] of substantial
public interest." 2 C.M.R. 06 096 002-8 to 002-9 § 17(C) (2003).
[2]
The nine standards that an applicant must
meet to receive a permit for activities that are regulated by NRPA
relate to (1) existing uses; (2) soil erosion; (3) habitats and fisheries;
(4) natural water flow; (5) water quality; (6) flooding;
(7) sand supply; (8) natural and recreational features of river segments;
and (9) dredging. 38 M.R.S.A. § 480-D (2001 & Supp.
2004).
[3]
The factors set forth in the Wetland Protection
Rules that are considered by the Board and the Department when conducting
section 480-D analyses include: whether a practicable alternative
to the proposed project exists, 2 C.M.R. 06 096 310-4 § 5(A)
(2002); whether the amount of wetland to be altered has been kept
to the minimum amount necessary, id. § 5(B); whether compensation is required, 2 C.M.R.
06 096 310-4 to 310-5 § 5(C) (2002); and whether the project
will have an unreasonable impact on a wetland, which includes the
cumulative impact standard, 2 C.M.R. 06 096 310-5 to 310-6 § 5(D)
(2002).
[4]
Other alternatives considered by the Ulianos
that were rejected by them, and by either the Department or the Board,
included using public facilities, installing a temporary, seasonal
pier, and constructing a shorter pier.
[5]
Contrary to the Ulianos' assertion, the
practicable alternatives rule does not result in a de facto moratorium
on coastal pier construction.
The Ulianos allege that the particular characteristics of their
shoreline make it infeasible to use a dinghy and a mooring to access
their boat. Consequently, the Ulianos argue that allowing
the Board to deny their permit application based on a finding that
using a dinghy and a mooring is a practicable alternative to their
pier would effectively cut off future coastal pier construction because
there would be no circumstances in which a dinghy and a mooring would
not constitute a practicable alternative to a pier.
The Board concedes, however, that it does not have the authority
to impose a moratorium, express or otherwise, on the permitting of
piers. If the existence of a practicable alternative
is just one factor the Board considers in its overall section 480-D
analysis, the fact that a practicable alternative to a proposed pier
exists will not necessarily result in the denial of a permit.
[6]
Though framed as an argument that the
Board's finding is contrary to the evidence and arbitrary and capricious,
the issue is actually whether the Board erred as a matter of law in
basing its cumulative impact finding on speculation that other piers
might follow.