Skip Maine state header navigation
Jenkins v. Walsh Bros.
MAINE SUPREME JUDICIAL COURT
Reporter of Decisions
Decision: 2002
ME 168
Docket: Yor-02-163
Submitted
on Briefs:
July 22, 2002
Decided: November
22, 2002
Panel: SAUFLEY,
C.J., and CLIFFORD, RUDMAN, ALEXANDER, CALKINS, and LEVY, JJ.
JENKINS, INC.
v.
WALSH BROTHERS, INC., et al.
LEVY, J.
[¶1] Walsh Brothers, Inc., the general
contractor for the construction of a new facility at the University of New
England, and Aetna Casualty & Surety Co. appeal from a judgment entered on
remand in the Superior Court (York County, Brennan, J.) awarding Jenkins, Inc., a drywall
subcontractor, prompt payment remedies pursuant to 10 M.R.S.A. §§ 1111-1120 (1997 & Supp. 2001). Walsh Brothers contends that the trial
court erred as a matter of law and as a matter of fact by imposing interest and
penalties pursuant to sections 1114(4),[1] 1116(4),[2] and 1118(2)[3] and that the trial court erred as a
matter of law by awarding Jenkins attorney fees pursuant to section 1118(4).[4]
Aetna contends that the entry of judgment against it was erroneous
because Jenkins waived its claim against Aetna and failed to prove the elements
of the claim at trial. We affirm
the award to Jenkins of interest, penalties, and attorney fees against Walsh Brothers pursuant to the
prompt payment statute and vacate the judgment against Aetna.
I. BACKGROUND
[¶2] The facts of this case are set forth in
Jenkins, Inc. v. Walsh Bros., Inc., 2001 ME 98, 776 A.2d 1229 ("Jenkins I"), in which we affirmed the judgment
against Walsh Brothers in part and remanded for further findings pursuant to
the prompt payment statute. Id. ¶¶ 29, 32, 776 A.2d at 1239-40. We stated that a subcontractor seeking
penalties under the prompt payment statute must establish the following four
elements:
(1) [T]he services were performed in
accordance with the agreement or understanding of the parties; (2) the owner
has made the progress or final payment; (3) the subcontractor has invoiced the
work; and (4) the contractor failed to make payment within seven days after
receipt of the invoice, or after receipt of the progress or final payment from
the owner, whichever is later.
Id. ¶
24, 776 A.2d at 1237. Applying
these four elements to the court's findings, we determined that "[t]he court found that Walsh did not
act in good faith and that Jenkins succeeded in meeting its burden on the first
two elements." Id. ¶ 25, 776 A.2d at 1237. Specifically,
the court found that Jenkins had performed the work and that UNE had made a
progress payment of $170,000 [to Walsh Brothers]." Id.
We also determined, however, that the court had not made findings
relative to the third and fourth elements.[5] Id. ¶ 26, 776 A.2d at 1237-38. We therefore remanded the case for
additional findings by the court to determine whether Jenkins met its burden of
proof:
Without a finding of the amounts due and
the dates from which the penalties should run, the court could not award
enhanced interest or a monthly penalty pursuant to sections 1114(4) and
1118(2). Therefore, we must vacate
the court's imposition of prompt payment penalties and remand for further
findings by the court to determine whether Jenkins met its burden of proof.
Id. ¶ 29, 776 A.2d at 1238-39.
[¶3] We also noted that there was a similar
lack of factual findings with regard to Jenkins's claim for penalties and
interest on the retainage pursuant to section 1116(4). Id. ¶ 27 n.13, 776 A.2d at 1238. In addition, we vacated the award of attorney fees pursuant
to section 1118(4) because we found that Jenkins had failed to prove its
entitlement to penalties pursuant to the prompt payment statute. Id. ¶ 32, 776 A.2d at 1240. We
instructed that "[i]f the court finds that Jenkins failed to establish a
violation of the statute, Jenkins has not prevailed 'within the scope of
[prompt payment statute],' and accordingly, the court may not award attorney
fees." Id. ¶ 32, 776 A.2d at 1240.
[¶4] On remand, the court held a
non-testimonial hearing and entered judgment for Jenkins and against Walsh
Brothers and Aetna. The court adopted the proposed findings submitted by
Jenkins and found that Walsh Brothers received the $170,000 payment for
Jenkins's work no later than November 14, 1996. It also found that Walsh Brothers received a $31,472.82
payment for the retainage related to Jenkins's work no later than April 30,
1997. Based upon these findings,
the court awarded interest, penalties, and attorney fees pursuant to the prompt payment
statute. The court also entered judgment against Aetna with
respect to the payment bond it had posted as security for Walsh Brothers's
performance of the UNE construction project. Jenkins's claim against Aetna was not addressed in the
court's original judgment, nor was the claim's omission from the original
judgment raised as an issue on appeal in Jenkins I.
II. DISCUSSION
A. Prompt Payment Remedies
[¶5]
Walsh Brothers asserts that there is no competent evidence to support the
court's findings regarding the payments and the dates by which they were
received. "Where there is
competent evidence in the record to support the court's findings, we will not
disturb the factual findings of the court." Sorey v. Sorey, 1998 ME 217, ¶ 14, 718 A.2d 568, 571. "When a trial court adopts verbatim the proposed findings of
a party, we must scrutinize the findings closely to determine whether the court
has adequately performed its judicial function." Weeks v. Weeks, 650 A.2d 945, 946 (Me. 1994).
[¶6]
The dates of the two payments are pivotal because the court must determine when
the payments were received in order to identify the dates from which prompt
payment remedies run. See Jenkins, 2001 ME 98, ¶ 24, 776 A.2d at 1237. Turning first to the date of the $170,000 payment, the
court's finding that the payment was made no later than November 14, 1996, was
based on Plaintiff's Exhibit 368, which is a summary of a construction progress
meeting held on November 14, 1996, prepared by Ellenzweig Associates, Inc., the
designer for the UNE project.
Paragraph 13 of the summary states:
13. Jenkins, Inc. - Lien
UNE stated that they were issued a
$400,000 lien on the building; Walsh Bros. stated that this firm had been paid
for their "work-in-place" (+/- $170,000).
The additional monies will be put in escrow.
This notation is susceptible to two
interpretations. First, that Walsh Brothers's representative stated that
Jenkins had been paid approximately $170,000 for its "work-in-place," and an
unspecified amount of additional money would be placed in escrow.
Second, that Walsh Brothers's representative stated that Jenkins had
been paid for its "work-in-place," and an additional sum, plus or minus
$170,000, would be placed in escrow.
The court's judgment reflects that it adopted the second of these two
interpretations of this exhibit.
This interpretation was supported by the testimony of Walsh Brothers's
employee Derek Manier, who was the project director on the UNE construction and
Walsh Brothers's sole representative at the November 14 progress meeting. Manier acknowledged that the notation
could be construed to mean that Walsh Brothers had received approximately
$170,000 intended for Jenkins that had been placed in escrow, but he denied
having made such a representation at the progress meeting.
[¶7] The meaning and weight to be given the
exhibits and the testimony of the witnesses is for the fact-finder to determine
and must be upheld unless clearly erroneous. Crowley v. Dubuc, 430 A.2d 549, 552 (Me. 1981). The court was not bound to accept Manier's recollection of
what he said at the construction progress meeting held several years prior to
the trial. The court's
interpretation of the exhibit was also consistent with the separate evidence it
received regarding the total amount Jenkins had invoiced and the total amount
Walsh Brothers had paid as of the November 14th meeting.[6] In addition, the court's construction of
Plaintiff's Exhibit 368 was consistent with the final sentence of paragraph 13
of the exhibit regarding the placement of "additional money in escrow." There is no apparent reason for the
participants to have discussed placing money in escrow unless Walsh Brothers
had received a payment or payments from UNE on or before November 14th related
to Jenkins's services that had not yet been paid to Jenkins.
[¶8] In keeping with section 1114(3), Walsh
Brothers was required to make payment to Jenkins within seven days of the last
invoice or within seven days of the payment to Walsh Brothers from UNE,
whichever was later. 10 M.R.S.A. §
1114(3). Therefore, combining the
court's finding of the $170,000 payment by November 14 with the finding that
$167,416.79 had been invoiced as of September 26, the "later" date for purposes
of establishing when the payment was due under section 1114(3) was November 21,
seven days after November 14.
[¶9]
With respect to the retainage, the court found on remand that Walsh Brothers
received payment of $31,472.82 from UNE for the retainage no later than April
30, 1997. Consequently, Walsh
Brothers was required to pay Jenkins the retainage within seven days, by May 7,
1997. The court's finding that UNE
paid Walsh Brothers retainage in the amount of $31,472.82 no later than April
30, 1997, was based upon Plaintiff's Exhibit 408. The exhibit is entitled "WALSH BROTHERS INCORPORATED
REQUISITIONS" and summarizes requisitions submitted by Walsh Brothers to
UNE. It reflects that Walsh
Brothers submitted requisition number 18 to UNE in the amount of $77,414 for
work completed during the period ending April 30, 1997. A notation accompanying requisition
number 18 states: "DRYWALL retainage reduced to 0%."
[¶10] The court's findings reflect that it
interpreted the notation in Plaintiff's Exhibit 408 that the "drywall retainage
reduced to 0%" to mean that as of the date of the requisition, April 30, 1997,
Walsh Brothers had been paid the amount of the retainage it had withheld from
Jenkins. The court's interpretation of the exhibit
is consistent with the separate evidence it received regarding the amounts
Jenkins had invoiced and Walsh Brothers had paid as of the November 14 meeting.
The court's finding that the retainage payment in the amount of $31,472.82 was
received by Walsh Brothers no later than April 30, 1997, is therefore supported
by competent evidence.
[¶11] Because we conclude that the court's
finding regarding Walsh Brothers's receipt of $170,000 by November 14, 1996, is
supported by competent evidence, a proper foundation existed for the imposition
of enhanced interest and penalties pursuant to sections 1114(4) and 1118(2). Id. ¶ 29, 776 A.2d at 1238-39. The same is true with respect to the retainage related
interest and penalties imposed by the court pursuant to section 1116(4) in
connection with Walsh Brothers's receipt of $31,472.82 by April 30, 1997. See id. ¶ 27 n.13, 776 A.2d at 1238. These findings also provided a proper foundation for the
court's award of attorney fees pursuant to section 1118(4).
B. Entry of Judgment Against Aetna
[¶12] In Jenkins I, we noted that Jenkins's claims against
UNE and Aetna were not before the Court on appeal:
UNE and The Aetna Casualty & Surety
Company were also named defendants but are no longer parties to this
action. The court granted summary
judgment in favor of UNE on Jenkins's lien claim, resolving count I of the
complaint. Count V, regarding a
bond issued by Aetna, was dismissed by agreement of the parties. Those counts are not before us.
Id., ¶ 5 n.4, 776 A.2d at 1233. Count V was the only count in which Jenkins sought relief
against Aetna. Following the
remand of this case, Jenkins argued to the Superior Court that our statement in
Jenkins I that the
count against Aetna had been dismissed by agreement of the parties was "an
error by the Law Court as to their status." Jenkins
explained that its failure to include relief against Aetna in the proposed
judgment it originally submitted to the court was an unintentional
oversight. Aetna responded at the
hearing that counsel for the parties had agreed at the outset that Aetna "was out
of the case." The trial justice
stated that he did not have a memory of what had been agreed by the parties,
but that "it was pretty clear . . . that Aetna was out of the case." The court ultimately relied on the
absence of any docket entry reflecting the dismissal of the claim against Aetna
when it included Aetna in the judgment, holding Aetna "jointly and severally
liable under Count V (payment bond claim) for all amounts included in paragraph
1" against Walsh Brothers.
[¶13] Aetna contends that the court's
inclusion of Aetna in the judgment issued following the remand is an abuse of
discretion because Jenkins failed to prosecute its claim against Aetna, and
that it is also clearly erroneous because Jenkins failed to prove the elements
of the claim. We do not reach
these issues, however, because we conclude that the court's award of relief
against Aetna exceeded the scope of our mandate in Jenkins I and must, therefore, be vacated.
[¶14] Although the merits of Jenkins's claim
against Aetna were not raised in Jenkins I, the status of the claim was considered because it was
necessary to our determination of whether the appeal was taken from a final
judgment. See Gagnon v.
Allstate Ins. Co., 635 A.2d 1312, 1314 (Me. 1994) (ruling
that Law Court generally only reviews judgments it deems final insofar as the
trial court's action fully decides the matter and no subsequent proceedings
will render the appellate court's decision immaterial). In the absence of a final judgment or
any of the narrowly defined exceptions to the final judgment rule, the Law
Court will not entertain an appeal.[7]
Based upon the record, briefs, and argument of counsel, we expressly
concluded in Jenkins I
that Jenkins's claim against Aetna had been voluntarily dismissed. This constitutes a determination on
appeal as to Aetna's status as a party to the action.
[¶15] Jenkins could have raised the failure
of the original judgment to award it relief against Aetna as an issue in its first appeal. Jenkins could have also sought our
reconsideration of the status of its claim against Aetna following the
certification of our decision in Jenkins I, based upon its belief, expressed subsequently to the
Superior Court, that we misapprehended the status of its claim against
Aetna. See M.R. App. P. 14(b)(1) (A motion for reconsideration may be filed
within fourteen days after the date of the decision and "shall state with
particularity the points of law or fact that in the opinion of the moving party
the Court has overlooked or misapprehended . . . ."). Jenkins failed, however, to seek appellate review of the
original judgment's silence as to Aetna and also failed to request
reconsideration of our opinion in Jenkins I.
[¶16] Jenkins argues that the court's entry
of judgment against Aetna following the remand was authorized by Rule 60(a) of
the Maine Rules of Civil Procedure which permits the correction of "[c]lerical
mistakes" in judgments "arising from oversight or omission." The inclusion of Aetna in the
judgment, however, reflects an effort to correct an error resulting from the
court's earlier understanding that Aetna was "out of the case." The court's authority under Rule 60(a)
does not extend to correcting a substantive error in a judgment. Compare Taylor v. Lapomarda, 1997 ME 216, ¶ 12, 702 A.2d 685, 689 (Rule 60(a) does not
authorize relief where claimant did not contend that judgment entered by court
failed to reflect the second verdict form returned by the jury, but rather
contended court failed to enter a judgment consistent with the jury's intent); with
Williams v. Williams, 645
A.2d 1118, 1122 (Me. 1994) (Rule 60(a) authorizes relief where court
inadvertently switched figure for wife's marital equity with amount of
mortgage).
[¶17] Because the question of Aetna's status
as a party defendant in this case was considered in Jenkins I, the entry of judgment against Aetna
following the remand of this case exceeded the scope of this Court's
mandate. See Meiners v. Aetna
Cas. & Sur. Co., 663
A.2d 6, 8 (Me. 1995) (trial court may not alter the Law Court's mandate
following appeal); Rose v. Osborne, 136 Me. 393, 400, 11 A.2d 345, 348 (1940) (trial court may not
enlarge, limit, or modify the scope of the Law Court's mandate). Accordingly,
the judgment against Aetna must be vacated.
The
entry is:
Judgment
affirmed as against Walsh Brothers, Inc. Judgment vacated as against Aetna
Casualty & Surety Co. and remanded to the Superior Court for entry of a
judgment of dismissal pursuant to M.R. Civ. P. 42(a)(2).
Attorney for plaintiff:
David P. Ray, Esq.
Bernstein, Shur, Sawyer & Nelson, P.A.
P. O. Box 9729
Portland, ME 04104-5029
Attorney for defendants:
Robert W. Harrington, Esq.
Law Offices of Robert W. Harrington
One Washington Mall
Boston, MA 02108
[1]
Addressing delayed payments to a subcontractor, section 1114(4) provides:
Notwithstanding any contrary agreement, if
any progress or final payment to a subcontractor or material supplier is
delayed beyond the due date established in subsection 2 or 3, the contractor or
subcontractor shall pay its subcontractor or material supplier interest on any
unpaid balance due beginning on the next day, at an interest rate equal to that
specified in Title 14, section 1602-A, subsection 2.
10 M.R.S.A. § 1114(4) (1997).
[2]
This section provides that "[i]f a contractor or subcontractor
unreasonably withholds acceptance of the work or materials or fails to pay
retainage as required by this section, the owner, contractor or subcontractor
is subject to the interest, penalty and attorney's fees provisions of this
chapter." 10 M.R.S.A. § 1116(4)
(1997).
[3]
This section provides that:
If arbitration or litigation is commenced
to recover payment due under the terms of this chapter and it is determined
that an owner, contractor or subcontractor has failed to comply with the
payment terms of this chapter, the arbitrator or court shall award an amount
equal to 1% per month of all sums for which payment has wrongfully been
withheld, in addition to all other damages due and as a penalty.
10 M.R.S.A. § 1118(2) (1997).
[4]
This subsection provides that "[n]otwithstanding any contrary agreement,
the substantially prevailing party in any proceeding to recover any payment
within the scope of this chapter must be awarded reasonable attorney's fees in
an amount to be determined by the court or arbitrator, together with
expenses." 10 M.R.S.A. § 1118(4)
(1997).
[5]
In
its original decision, the Superior Court found that "[a]s the
project was wrapping up Walsh received payments from U.N.E. for drywall
work of $170,000 and failed to make any payment to Jenkins."
There was no finding made as to the date by which UNE made the payment
to Walsh, other than it was received "[a]s the project was wrapping
up . . . ."
[6]
The parties stipulated that the date of Jenkins's last regular invoice
to Walsh Brothers was September 20, 1996.
As of that date, the total amount invoiced by Jenkins exceeded the total
of all payments by $198,889.60.
The court separately found that $31,472.82 of the amount owed to Jenkins
was for the retainage. Therefore,
the balance in unpaid contract invoices as of the November 14 meeting was
$167,416.79, which is
approximately the same amount as the payment the court determined Walsh
Brothers had received from UNE, but had not paid to Jenkins as of that date.